Location: Martinsburg, WV
Duration: 20 weeks
Vezér Industrial Professionals installed the Loesche Mill 60.6 at a brown field cement plant expansion in Martinsburg, WV. The project included installing all raw mill associated equipment.
Scope of Work:
- Install Mill Bases
- Install Joint Blocks
- Check alignment after completing welding of Joint Blocks and correct any possible misalignment
- Perform the final level centering of the mill base
- Tension mill base anchor bolts to 100% of specified torque value
- Finish Grout of Mill Bases
- Install Gear Frame
- Pressure grouting with Epoxy Grout
- Install Main Gear
- Assembly Bottom Casing
- Assembly Grinding Table
- Roller and Pressure Lever Assembly (Roller and Swing lever assembly delivered assembled)
- Swinging out the Roller Shaft Boss Assembly
- Installing the Spring Box Assembly Connecting the Hydraulic Cylinder to the Joint head
- Install Steel Platform
- Install Mill Housing (it is assumed that mill housing is delivered in three sections)
- Nozzle Ring
- Assembling Separator, including classifier and drive
- Rotary Valve
- Installation Hydraulic System